Mumbai-Ahmedabad bullet train project hits 59.1% physical progress as spending crosses ₹90,396 crore

Mumbai-Ahmedabad bullet train project showing 59.1 percent progress and ₹90,396 crore spending
Infographic showing progress and key metrics of the Mumbai-Ahmedabad bullet train project. Representative Image (Generated using Google AI)

The Mumbai-Ahmedabad High Speed Rail (MAHSR) project has achieved 59.1% physical progress till March 2026, according to the latest government data.
The 508 km corridor, which is India’s first bullet train project, has an original project cost of ₹1,08,000 crore.
The high-speed rail corridor has crossed 58 per cent physical progress, according to the monthly project monitoring flash report of the Ministry of Statistics and Programme Implementation (MoSPI) for the month of March.

As per the report, ₹90,396 crore has been spent so far on the bullet train project.

The Mumbai-Ahmedabad High-Speed Rail project, initially pegged at ₹1.08 lakh crore, is now reportedly estimated to cost around ₹1.98 lakh crore, a significant jump from its original projection, with the revised figure reportedly awaiting final Cabinet approval.

Financing for the project includes low-interest loans of about ₹88,000 crore from the Japan International Cooperation Agency.

The additional cost on the project will reportedly be borne by the government, with no further funding expected from the Japanese agency.

The project is being executed by the National High Speed Rail Corporation Limited, a special purpose vehicle set up in 2016 to implement high-speed rail infrastructure in the country.

Read also : India’s first bullet train project advances with 185 Km RC track bed laid, 70 Km track slab installation completed

Progress on the corridor was affected by delays in land acquisition and disruptions during the coronavirus pandemic.

While operations were earlier planned to begin in 2022, full completion is now targeted by 2029.

Providing an update on timelines, Railway Minister Ashwini Vaishnaw had earlier in January said the first bullet train service is expected to run on 15 August 2027, starting with the Surat-Bilimora section.

The corridor will be opened in phases, covering the Vapi-Surat, Vapi-Ahmedabad, and Thane-Ahmedabad stretches before the Mumbai-Ahmedabad section becomes operational in the final stage.

The MAHSR corridor spans 352 Km in Gujarat (348 Km) and Dadra and Nagar Haveli (4 Km), and 156 Km in Maharashtra.

The 508 km corridor will pass through Gujarat, the Union Territory of Dadra and Nagar Haveli, and Maharashtra with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad, and Sabarmati.

Read also : Indian Railways’ plantation drive adds 81.59 lakh trees across zones in 2025-26, supporting safer and greener operations