Phulbani, November 9: Traffic has resumed on the Kalinga Ghat section of National Highway 157 in Odisha’s Kandhamal district after a 46-day closure caused by heavy rainfall and landslide damage, restoring an important road connection between Kandhamal and neighbouring Ganjam district.
Kandhamal district authorities permitted all categories of vehicles to use the Kalinga Ghat road from November 7 following repairs. However, heavy vehicles remain restricted on the Daringbadi–Gajalbadi Ghat route, which has reopened only to light motor vehicles because the repairs are temporary.
According to local reports, Kandhamal Collector Vedbhushan authorised the reopening after restoration work made the Kalinga Ghat stretch suitable for traffic.
The road had been closed from September 23 amid heavy rainfall and landslide risks. Rockfalls, including a large boulder that blocked the highway, and damage to sections of the road contributed to the prolonged disruption.
The closure affected travel between Kandhamal and Ganjam, forcing commuters and transport operators to use alternative routes.
Some motorists reportedly had to travel an additional 20 to 30 kilometres, increasing journey times and transport costs.
The National Highways Authority of India (NHAI) undertook restoration work on the damaged Kalinga Ghat stretch. However, recurring rainfall and difficult terrain delayed the repairs.
Following the restoration work, the district administration allowed light and heavy vehicles to resume movement from November 7. The permission will remain valid until further orders.
The reopening is expected to benefit residents, daily commuters, passenger transport operators and businesses that depend on the highway for travel and the movement of goods between the two districts.
Meanwhile, the Daringbadi–Gajalbadi Ghat road has also reopened following a separate closure that began on October 27.
The route suffered damage following heavy rainfall associated with Cyclone Arnab, prompting the district administration to suspend traffic.
However, the repairs carried out on this road are temporary. As a precaution, the administration has permitted only light motor vehicles to use the stretch.
Heavy vehicles will remain barred until the authorities consider the road suitable for their movement.
The district administration has directed the police, National Highways officials and other relevant authorities to enforce the restrictions.
As a result, all categories of vehicles can now use Kalinga Ghat, while heavy commercial vehicles and other restricted vehicles cannot travel through the Daringbadi–Gajalbadi Ghat route.
Although the reopening has restored an important transport connection, concerns remain about the long-term safety of the landslide-prone hill roads.
Repeated rainfall, rockfalls and road damage have highlighted the challenges of maintaining reliable connectivity through the region’s difficult terrain.
According to local reporting, a highway engineer said a Detailed Project Report (DPR) would be prepared for permanent reconstruction and widening of the Kalinga Ghat road and submitted to NHAI.
However, the proposed permanent works have not yet been approved. No funding allocation, construction start date or completion timeline has been announced.
These longer-term measures are separate from the repairs that enabled traffic to resume on November 7.
For now, the reopening of Kalinga Ghat has ended a prolonged disruption for commuters and transport operators travelling between Kandhamal and Ganjam.
However, the Daringbadi–Gajalbadi Ghat route remains partially restricted,
Read also: No stopping at toll booths: NHAI issues new guidelines to expand barrier-free highway tolling